Mining News

Perseus unveils new LoM plan at Yaouré

Share on facebook
Share on twitter
Share on linkedin
Share on email

Gold miner Perseus Mining has estimated that the Yaouré gold project, in Cote d’Ivoire, could produce some 1.43-million ounces over a mine life of an initial eight years.

In an updated life-of-mine (LOM) plan for the West African operation, ASX and TSX-listed Perseus noted that the project would produce an average of 260 000 oz/y of gold between 2022 and 2024, at an average all-in sustaining cost of some $745/oz over the mine life.

The new LOM plan has updated the measured and indicated mineral resource at Yaouré to 51.3-million ounces, grading 1.34 g/t gold for 2.21-million ounces of gold, at a cut-off grade of 0.4 g/t gold